top of page

CONSULTATION LIBRARY

12 June 2024 – Additional information submitted to PEDW.

Applicant’s Introduction to the Variation Submission

​Cover Letter & Application Index

The following new drawings and documents accompany the Variation Submission & Applicant’s Regulation 15 response:

Planning Application Drawing  

Drawing No SK06 Rev A – Potential Widening of Southern Roundabout Arm

​

Green Infrastructure Strategy

the GIS presents how the submitted planning information and documents evidence that green infrastructure has been incorporated into the proposal from project inception, throughout the design and promotion process and will be secured for the lifetime of the proposed development. The GIS also demonstrates that in substance the requirements of Chapter 6 of PPW (and the stepwise approach) have been robustly addressed

​

LVIA Addendum

The LVIA Addendum provides additional information in relation to the potential cumulative effects of Swansea Local Development Plan (LDP) allocated site SD H: North of Waunarlwydd/Fforestfach in combination with the Proposed Development and should be read in conjunction with the Landscape and Visual Impact Assessment (LVIA) provided by Pegasus in December 2023

​

Transport Statement

The Transport Statement (TS) has been produced to respond to the post acceptance consultee response provided by Swansea Council as the Highways Authority, which specifically asked that a TS be prepared to accompany the application

​

Outline Landscape and Ecological Management Plan*

*The Outline LEMP supersedes the LEMP presented at Appendix 7 of the submitted Ecological Appraisal

​

Applicant’s Regulation 15 Response

This document provides the applicant main response to the Inspector’s request for further information

​

Technical Note in response to Dwr Cymru consultation comments on the proposed DNS application

This technical note supplements the Applicant’s Regulation 15 response

​

Statement of Common Ground on Planning Conditions

​

Applicant’s Response to Local Impact Report and other Representations

​

Technical Note on Flood Displacement and Compensation

This technical note responds to the Natural Resources Wales (NRW) comments which relate to the displacement of flood water onto the neighbouring water treatment works which are considered to be under risk of flood already

​

Wintering Bird Survey: Addendum

This addendum presents the findings of the wintering bird surveys undertaken from October 2023 to March 2024

​

Collaborative Benefits Report Update

This note is to provides the Inspector with an update on the Collaborative Benefits Report (CBR) with respect to the negotiations with Gower Power on the Community Shared Ownership

Planning application drawings

​

PSC 100 001  V15   Proposed Layout Plan

​

PSC 100 102  V14  Proposed Site Layout Sheet 1 (Scale 1:500)

​

PSC 100 103  V14  Proposed Site Layout Sheet 2 (Scale 1:500)

​

PSC 100 104  V14  Proposed Site Layout Sheet 3 (Scale 1:500)

​

PSC 100 105   V14  Proposed Site Layout Sheet 4 (Scale 1:500)

 

PSC 100 106  V14  Proposed Site Layout Sheet 5 (Scale 1:500)

​

PSC 100 107  V14  Proposed Site Layout Sheet 6 (Scale 1:500)

​

PSC 100 108  V14  Proposed Site Layout Sheet 7 (Scale 1:500)

​

PSC 100 109  V14  Proposed Site Layout Sheet 8 (Scale 1:500)

​

PSC 100 110  V14  Proposed Site Layout Sheet 9 (Scale 1:500)

​

PSC 100 111  V14  Proposed Site Layout Sheet 10 (Scale 1:500)

​

PSC 100 112  V14  Proposed Site Layout Sheet 11 (Scale 1:500)

​

PSC 100 113  V14  Proposed Site Layout Sheet 12 (Scale 1:500)

​

PSC 100 114  V14  Proposed Site Layout Sheet 13 (Scale 1:500)

​

PSC 100 115  V14  Proposed Site Layout Sheet 14 (Scale 1:500)

​

PSC 100 116  V14  Proposed Site Layout Sheet 15 (Scale 1:500)

​

PSC 100 117  V14  Proposed Site Layout Sheet 16 (Scale 1:500)

 

PSC 100 118  V14  Proposed Site Layout Sheet 17 (Scale 1:500)

​

PSC 100 119  V14  Proposed Site Layout Sheet 18 (Scale 1:500)

​

PSC 100 120  V14  Proposed Site Layout Sheet 19 (Scale 1:500)

​

PSC 100 121  V14  Proposed Site Layout Sheet 20 (Scale 1:500)

​

PSC 100 122  V14  Proposed Site Layout Sheet 21 (Scale 1:500)

​

PSC 100 123  V14  Proposed Site Layout Sheet 22 (Scale 1:500)

​

PSC 100 124  V14  Proposed Site Layout Sheet 23 (Scale 1:500)

​

SC PJ 55 02-150-23  C  Overall Cable Route Plan

​

SC PJ 55 02-150-24  C  Cable Route Plan
Sheet 01 of 05

​

SC PJ 55 02-150-25  C   Cable Route Plan
Sheet 02 of 05 

​

SC PJ 55 02-150-26  C  Cable Route Plan
Sheet 03 of 05 

​

SC PJ 55 02-150-32  C  Cable Route Plan
Sheet 04 of 05 

​

SC PJ 55 02-150-33  C  Cable Route Plan
Sheet 05 of 05

​

​SC PJ 55 02-150-31  4  132kV Cable
Route Trench Sections

​

SC PJ 55 02-150-27   4  132kV
Cable Route - Option 2 

ORIGINAL PLANNING APPLICATION

Application Drawings

​

NG proposed tower works north 17_230655_03_A​

​

NG proposed tower works south 17_220550_04_A

​

P21-2998_13L GI Plan

​

PCS Array Table Cross Section 07.12.2023.V3

​

PCS Fence and CCTV Detail  24.11.2023

​

PCS Gate Detail  24.11.2023

​

PCS Site Road Cross Section 28.11.23 V1

​

PSC_Spare Parts Container Details_rev0_31.01.22

​

SC PJ 55 01-150-29 - WPD Tower Plan & Elevation

​

SC PJ 55 02-150-07 - AET Plan & Foundation

​

SC PJ 55 02-150-07 - Proposed Site Plan - Rev 6

​

SC PJ 55 02-150-08 - Auxilliary Transformer Plan & Elevation

​

SC PJ 55 02-150-09 - Battery Container Plan & Elevation

​

SC PJ 55 02-150-10 - BCP Plan & Elevation

​

SC PJ 55 02-150-11 - CCTV & Lighting Plan & Elevation

​

SC PJ 55 02-150-12 - Control Room and HV Switchroom Elevation

​

SC PJ 55 02-150-13 - Grid Transformer Plan & Elevation

​

SC PJ 55 02-150-14 - NER Plan & Elevation

​

SC PJ 55 02-150-15 - NG Substation Plan & Elevation

​

SC PJ 55 02-150-16 - PCS Inverter Skid Plan & Elevation

​

SC PJ 55 02-150-17 - Transformer Skid Plan & Elevation

​

SC PJ 55 02-150-18 - Proposed Site Levels - Rev 4

​

SC PJ 55 02-150-19 - Proposed Site Sections - Rev 4

​

SC PJ 55 02-150-20 - BOP & 132kV Compound Fencing Details - Rev 2

​

SC PJ 55 02-150-22 - Site Elevation - Rev 4

​

SC PJ 55 02-150-23 - Overall Cable Route Plan Rev B

​

SC PJ 55 02-150-24 - Cable Route Plan Sheet - 01 of 05 Rev B

​

SC PJ 55 02-150-25 - Cable Route Plan Sheet - 02 of 05 Rev B

​

SC PJ 55 02-150-26 - Cable Route Plan Sheet - 03 of 05 Rev B

​

SC PJ 55 02-150-32 - Cable Route Plan Sheet - 04 of 05 Rev B

​

SC PJ 55 02-150-33 - Cable Route Plan Sheet - 05 of 05 Rev B

​

SC PJ 55 02-150-27 - 132kV Cable Option 2 Rev B

bottom of page